The PUD downtown undergrounding work is starting next week. 

 

Here is the schedule for the coming week:

Monday August 13, 2018

PUD contractor mobilizing to Port Townsend and receiving material from PUD.

Tuesday August 14, 2018

  • During the day pull in primary and secondary wire and terminate.  This is from the area next to the Subway building to the Ichikawa building and the primary vaults in front of the Plaza.
  • Planned outages for the Ferry Terminal and the Plaza from 9pm-2am.

Wednesday August 15, 2018

  • During the day install the transformer next to Ichikawa.
  • Planned outages for the Subway building, Windermere, US Bank, and Ichikawa from 9pm-2am.

Thursday August 16, 2018

Remove overhead secondary wire and de-mobilize.

 